Australia: The framework is in place for a new wallboard plant that Knauf Plasterboard is building at the Port of Bundaberg in Queensland. A 27.8km gas pipeline that will support the project has also been laid, according to the Bundaberg Newspaper. The next step will be to commission the pipeline and commission off-takes. First gas flows are scheduled for mid-February 2017 whereupon it will supply the new Knauf plant that is expected to start production in June 2017.