US: United States Gypsum (USG) has received a 1.750ML/day water use permit for a planned wallboard and joint compound (spackle) manufacturing plant near the Duke Energy complex in the city of Crystal River, Florida.
In 2011 USG bought 0.716km2 of land near the Progress Energy Florida power plant, now Duke Energy, to warehouse synthetic gypsum that is created by scrubbers at the coal-burning plants. USG takes all of the gypsum produced at the plant and moves it to the site by conveyor belt.
USG now plans to construct a gypsum processing facility at the site. Part of the water permit detailed a request for two 30.5cm wells to be located on the plant site, to which water will be piped. The plant will run six days a week, possibly seven during the peak building season.
Progressive Water Resources, which is handling the application process for USG, also investigated using reclaimed wastewater from Crystal River. However, that water has already been committed to Duke Energy.